These days, S-Curves are being made compulsory in the progress reports. S-Curve is nothing but display of labor units, Cumulative costs or other quantities against time. If it is a must to generate the S-Curve without having proper information on Costing and resources, there is a trick to generate the Curve with the dummy resource weights Let's see how we can generate the S-Curve Step-1 : Develop a schedule with proper WBS. Step-2 : Go to Resources tab and Right click, select Add to create a resource of Resource Type as " Labor ". Step-3 : Go to Activities Tab and click on Columns icon to add columns " Resources" , "Budgeted Labor units" , and "Actual Labor units" . Step-4: Now assign the labor resources to all the activities by selecting all the activities (using shift button) at a time and by holding Shift button left click on the resources cell of the last activity and select the created resource so as to assign res