Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels




In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel.

After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS.

So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6.

This is my sample schedule in primavera,

1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it.

2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity.

3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2

4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity.

5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule.

And Now let us color the WBS levels.

1. Select the entire Data range.

2. Go to Conditional Formatting and click on New Rule

3. Select Use a formula to determine which cells to format option

4. Type the formula as =and($A1=0,$C1="") (keep the dollar symbol on left side to both the cells). we are adding the Cell C1 reference so as to avoid coloring of the activity level, though the WBS level is being reflected for activities.

5. Select a color for WBS Level 0 Say blue color. Click OK. Click OK again.

6. Now, all those WBS Levels 0 will have the Blue color.

7. Similarly create rules for other WBS Level: 1, 2, 3, 4, 5.....

In this way, finally, you will be generating a colorful report alike Primavera P6 Schedule.

So, friends, this is all about this trick If you have enjoyed this tutorial, please give me a like, share and comment. For further more interesting videos, please do subscribe dptutorials

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Tags:
primavera p6 training online, primavera p6, primavera p6 training, primavera p6 tutorial, oracle primavera, primavera p6 download, primavera 6, oracle primavera p6, primavera p6 free download, primavera project management, primavera project planner, primavera download, primavera online, primavera training, primavera software free download, youtube primavera, primavera tutorial, is primavera online easy, p6 online, primavera p6 complete video tutorial free download

Comments

  1. Very nice blog and articles. I am realy very happy to visit your blog. Now I am found which I actually want. I check your blog everyday and try to learn something from your blog. Thank you and waiting for your new post.pmp certification in malaysia

    ReplyDelete
  2. Cordial saludo. He intentado insertar en excel la formula expuesta en el punto 3 "((FIND (TRIM (B2), B2)) - 1) / 2" sin las comillas dobles claro. Me retorna un error de #¡VALOR!...uso Excel en español, por lo tanto las funciones son "((ENCONTRAR(ESPACIOS (B2); B2)) - 1) / 2".

    Que puede estar ocurriendo?

    ReplyDelete
  3. Comentario adicional a mi consulta anterior, separe la formula para estudiarla quedando de la siguiente manera:

    =+ENCONTRAR(" ";B2) (Español)
    =+FIND(" ";B2) (Inglés)

    Tomando un cronograma de ejemplo que trae primavera p6 tomo la primera línea la cual es "EC00515 City Center Office Building Addition" sin las comillas dobles. Contando manualmente son 6 espacios, pero Excel en la formula retorna 8, al cual de acuerdo al resto de tu formula se le resta 1, quedando en 7 y se divide entre 2, lo cual arroja como resultado 3,5. Es esto correcto?...Por qué excel arroja 8 espacios cuando son 6?

    ReplyDelete
  4. Schedule your staff in seconds with UK’s leading Staff Rota Software· Get work rota for efficient Employee Scheduling Software that save your time and money.

    ReplyDelete
  5. primavera course in pakistan course equips individuals with skills to effectively use Primavera, making them valuable assets across industries requiring efficient project management and scheduling.

    ReplyDelete

Post a Comment