How to create a New User Defined Calendar in MS Project 2010

The Default Calendar in Microsoft Project is the Standard 5 Day Week Calendar, and we have the Two other calenders in the Global.MPT which are "24 Hrs" and "Night Shift".

You can change the Working Timings to change the calendar.Here is the process for this

Step 1: 

Open the Microsoft Project 2010 and go to "Project" in the menu bar and then click on "Change Work Time"

Step 2:

Then in the Wizard "Change Work Time". Click on the "Create a New Calendar"


Step 3 : 

In the Wizard, Type the Desired Calendar name, here i am typing as the "6 Days Calendar". and then Click "OK"


Step 4:

Then in the Wizard, Select the "Work Weeks" at the bottom and click on "Details" at the right side of the wizard.


Step 5:

Now here, Observe that all the 5 working days will be having the working timings as 9:00 AM to 5:00 PM. So select the 6th day Sat'day and Select "Set Day(s) to these Specific Working times:" on the right side and specify the timings at the bottom of the window.




Step 6:

Now, the Work Timings has been changed with a new calendar. So, to assign the newly created calendar to the Project that we are working now.Go to Project>>Project Information>>


and then select the Calendar in the Drop Down List. You will be able to view the newly created calendar "6 days Calendar". Select the same.


Watch a Video of this Exercise for better understanding.

Back to MS Project>>

Comments

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...