How to create a New User Defined Calendar in MS Project 2010

The Default Calendar in Microsoft Project is the Standard 5 Day Week Calendar, and we have the Two other calenders in the Global.MPT which are "24 Hrs" and "Night Shift".

You can change the Working Timings to change the calendar.Here is the process for this

Step 1: 

Open the Microsoft Project 2010 and go to "Project" in the menu bar and then click on "Change Work Time"

Step 2:

Then in the Wizard "Change Work Time". Click on the "Create a New Calendar"


Step 3 : 

In the Wizard, Type the Desired Calendar name, here i am typing as the "6 Days Calendar". and then Click "OK"


Step 4:

Then in the Wizard, Select the "Work Weeks" at the bottom and click on "Details" at the right side of the wizard.


Step 5:

Now here, Observe that all the 5 working days will be having the working timings as 9:00 AM to 5:00 PM. So select the 6th day Sat'day and Select "Set Day(s) to these Specific Working times:" on the right side and specify the timings at the bottom of the window.




Step 6:

Now, the Work Timings has been changed with a new calendar. So, to assign the newly created calendar to the Project that we are working now.Go to Project>>Project Information>>


and then select the Calendar in the Drop Down List. You will be able to view the newly created calendar "6 days Calendar". Select the same.


Watch a Video of this Exercise for better understanding.

Back to MS Project>>

Comments

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad