How to create a New User Defined Calendar in MS Project 2010

The Default Calendar in Microsoft Project is the Standard 5 Day Week Calendar, and we have the Two other calenders in the Global.MPT which are "24 Hrs" and "Night Shift".

You can change the Working Timings to change the calendar.Here is the process for this

Step 1: 

Open the Microsoft Project 2010 and go to "Project" in the menu bar and then click on "Change Work Time"

Step 2:

Then in the Wizard "Change Work Time". Click on the "Create a New Calendar"


Step 3 : 

In the Wizard, Type the Desired Calendar name, here i am typing as the "6 Days Calendar". and then Click "OK"


Step 4:

Then in the Wizard, Select the "Work Weeks" at the bottom and click on "Details" at the right side of the wizard.


Step 5:

Now here, Observe that all the 5 working days will be having the working timings as 9:00 AM to 5:00 PM. So select the 6th day Sat'day and Select "Set Day(s) to these Specific Working times:" on the right side and specify the timings at the bottom of the window.




Step 6:

Now, the Work Timings has been changed with a new calendar. So, to assign the newly created calendar to the Project that we are working now.Go to Project>>Project Information>>


and then select the Calendar in the Drop Down List. You will be able to view the newly created calendar "6 days Calendar". Select the same.


Watch a Video of this Exercise for better understanding.

Back to MS Project>>

Comments

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...