Finish date doesn't get changed, when you change the duration in primavera

We do face this problem of Finish date of the activity not getting changed, when we change the duration of the activity. Now, let us see the example and learn how to fix this issue.

If you see the Activity A1030 in the below primavera schedule, the duration of the activity is 5 days and finish date as 24-Mar-14.

 and now let's see the change in the Finish date by changing the duration from 5 days to 15 days and observe that there is no change in the Finish Date.

and  this error is being caused as the primavera is not calculating the remaining duration of this activity when the original duration is being changed. In fact, we observe that the change we are making by increasing  original duration of the activity is not linking with the remaining duration. This is the situation where everyone gets panic and finally land upon the solution of adjusting the remaining duration as the tool doesn't automatically calculate the new remaining duration when the original duration is being changed.

And now let us actually see the simple solution to fix this bug.

Step 1:

Click on the Project

Step 2:

Select the Project that you are working right now as shown in the picture below and go to the Calculations tab in the project details window at the bottom of the screen.


Step 3:

And now observe that in the Calculations tab, " Link budget and At completion for not started activities" is unchecked.
Now Check (tick) this check box and click "OK, and  you will get a pop-up window saying that all the durations will be recalculated for the not started activities.So, it is recommended to keep this checkbox ticked all the time so as to enable this function

Now Click Yes.

And now lets check

Step 4:

Go to Activities tab

Step 5:

Now change the duration of the activity from 5 to 15 days for the activity A1030 and observe that the Finish date automatically changing from 24-Mar-14 to 07-Apr-14



That's it. I hope this clears the issue.

Back to Primavera>>

Comments

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Primavera P6 Tutorial : Chapter 2.5 : Budgets

Budget Consists of quantities and cash flow required to complete a project. In the Planning stage project manager and other stakeholders need to estimate scope and budgets. As the scope changes, budget also needs to be adjusted to compensate. Primavera is helpful in establishing these budgets and tracking the changes in the budgets. In this Tutorial, let us learn how to establish budgets, establish monthly spending plans, implement changes to it and tracking monthly spending and variances right from EPS to Project and to WBS level. In the planning stage, we start the budgeting from the top level, like dividing the budget available to the EPS nodes for the duration of the projects. And then respective managers divide this budget to the projects for which they are responsible in each EPS node. Let us consider with an example here. Considering that we have $6000 allotted for an EPS node and it is having two projects and we divide this $6000 equally to these two projects as $3000 eac...