Skip to main content

Finish date doesn't get changed, when you change the duration in primavera

We do face this problem of Finish date of the activity not getting changed, when we change the duration of the activity. Now, let us see the example and learn how to fix this issue.

If you see the Activity A1030 in the below primavera schedule, the duration of the activity is 5 days and finish date as 24-Mar-14.

 and now let's see the change in the Finish date by changing the duration from 5 days to 15 days and observe that there is no change in the Finish Date.

and  this error is being caused as the primavera is not calculating the remaining duration of this activity when the original duration is being changed. In fact, we observe that the change we are making by increasing  original duration of the activity is not linking with the remaining duration. This is the situation where everyone gets panic and finally land upon the solution of adjusting the remaining duration as the tool doesn't automatically calculate the new remaining duration when the original duration is being changed.

And now let us actually see the simple solution to fix this bug.

Step 1:

Click on the Project

Step 2:

Select the Project that you are working right now as shown in the picture below and go to the Calculations tab in the project details window at the bottom of the screen.


Step 3:

And now observe that in the Calculations tab, " Link budget and At completion for not started activities" is unchecked.
Now Check (tick) this check box and click "OK, and  you will get a pop-up window saying that all the durations will be recalculated for the not started activities.So, it is recommended to keep this checkbox ticked all the time so as to enable this function

Now Click Yes.

And now lets check

Step 4:

Go to Activities tab

Step 5:

Now change the duration of the activity from 5 to 15 days for the activity A1030 and observe that the Finish date automatically changing from 24-Mar-14 to 07-Apr-14



That's it. I hope this clears the issue.

Back to Primavera>>

Comments

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...