Skip to main content

Finish date doesn't get changed, when you change the duration in primavera

We do face this problem of Finish date of the activity not getting changed, when we change the duration of the activity. Now, let us see the example and learn how to fix this issue.

If you see the Activity A1030 in the below primavera schedule, the duration of the activity is 5 days and finish date as 24-Mar-14.

 and now let's see the change in the Finish date by changing the duration from 5 days to 15 days and observe that there is no change in the Finish Date.

and  this error is being caused as the primavera is not calculating the remaining duration of this activity when the original duration is being changed. In fact, we observe that the change we are making by increasing  original duration of the activity is not linking with the remaining duration. This is the situation where everyone gets panic and finally land upon the solution of adjusting the remaining duration as the tool doesn't automatically calculate the new remaining duration when the original duration is being changed.

And now let us actually see the simple solution to fix this bug.

Step 1:

Click on the Project

Step 2:

Select the Project that you are working right now as shown in the picture below and go to the Calculations tab in the project details window at the bottom of the screen.


Step 3:

And now observe that in the Calculations tab, " Link budget and At completion for not started activities" is unchecked.
Now Check (tick) this check box and click "OK, and  you will get a pop-up window saying that all the durations will be recalculated for the not started activities.So, it is recommended to keep this checkbox ticked all the time so as to enable this function

Now Click Yes.

And now lets check

Step 4:

Go to Activities tab

Step 5:

Now change the duration of the activity from 5 to 15 days for the activity A1030 and observe that the Finish date automatically changing from 24-Mar-14 to 07-Apr-14



That's it. I hope this clears the issue.

Back to Primavera>>

Comments

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad