Unable to change the Original Duration in Primavera P6??

Here is a case when we are unable to change the original duration field once the schedule has been scheduled. This is because the activity has already been started. Let's get into detail explanation:

The Start and Finish Dates which we see at the time of preparing a schedule will be locked as planned start and Planned finish respectively.So, any change to the Original Duration can be seen with a change in the Planned Finish/Finish.

When a Task has not started:
Planned Dates and Start,Finish Dates are linked to each other
Lets see with an Example: Where Planned dates are same as the Start/Finish Dates


When a Task is in Progress:
The Planned Start Date Remains Unchanged if the Actual Start Date is different from the Original Planned Date.
Here in the example, lets status the schedule with actual date of Activity 1 as "26-Dec-14" and schedule(F9) it. you will observe the following changes in the schedule

  1. Planned Start date remains unchanged. 
  2. Original Duration will also be changed as it adds up the difference of Actual Start and Planned Start i.e 18 working days, so the original duration has become 38 from the previous 20 days.
  3. And the Finish Date/Planned Finish will now be equal to Planned Start Date +Original Duration.


When a Task is Completed:
The Planned Date are un linked from all the Date fields.

Back to Primavera>>

Comments

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...