How To Merge Two Separate Schedules Into One Master Schedule In Primavera



In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6.

In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject.

First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules.

1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here.

2. Go to Import, select XER format, Click Next

3. Select Project and click Next

4. Now select the Subproject .xer file from the Desktop and click Next

5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open.
Click Next and Finally Click on Finish.

6. Please note and make sure that your WBS and activity IDs should not conflict with each of the projects.

7. Now you can see the result as per your requirement that a master integrated schedule has been prepared.


In this way, one can prepare a Master Schedule, where you need to Integrate separate project schedules into One.

So, friends, this is all about this trick

If you have enjoyed this tutorial, please give me a like, share and comment. For further more interesting videos, please do subscribe dptutorials

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Tags:
primavera p6 training online, primavera p6, primavera p6 training, primavera p6 tutorial, oracle primavera, primavera p6 download, primavera 6, oracle primavera p6, primavera p6 free download, primavera project management, primavera project planner, primavera download, primavera online, primavera training, primavera software free download, youtube primavera, primavera tutorial, is primavera online easy, p6 online, primavera p6 complete video tutorial free download

Comments

Post a Comment

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...