Skip to main content

Primavera-1:5

Adding Activities, Relationships and scheduling 

Activities are the Fundamental work elements of a project. They are the lowest level of a work breakdown structure(WBS) and as such, are the smallest subdivision of a project that directly concerns the project manager 
You can define Following information for an activity 
Activity ID and Name
Activity Calendars, Start and Finish Dates
Activity type, duration type, and percent complete type.
WBS element and Activity codes
Constraints
Expenses
Predecessor and successor relationships
Work Products and deliverables
Resource and Roles
Notes and Feedback



Steps
To Add Activities, Click on Activities in the Home page or Project>Activities 
Organize Layout based on WBS & SORT by Activity ID 
Add Activities to respective WBS Level by clicking on ADD on command Bar button 

There are 6 types of Activity Types
 1.Task Dependent –> In a fixed duration
 This is the default activity type in P6.
 2.Resource Dependent
 3.Level of Effort
 4.Start Milestone
 5.Finish Milestone
 6.WBS summary

Activity Steps 

Steps allow you to break activities into smaller units and track the completion of those units.

Activity % Complete type 

The way in which the percent complete for the selected activity is determined 

There are 3 types in this 
Duration Type 
Physical Type 
Units Type

Relationships 

A Relationship defines how a Activity relates to the start or finish of another activity. These Relationships form a logic to your project and are used together for determining Schedule dates.

 Relationship Types

Finish to Start (Default)
Finish to Finish
Start to Start
Start to Finish
How to Assign Relationships?

Select an Activity and select its successor from “successor” tab in the activity detail form

Activity details can be enabled from the list of tool bars shown on the top of the layout.

Assigning Calendars and Activity codes

  • To Assign Calendars/activity code select the activity and enable activity details 
  • In Activity details click  on General/Codes Tab 
  • Click on Assign and select the respective calendar/codes.

Scheduling 

Scheduling can be done in two ways 
When you choose the schedule command or each time you make a change that affect schedule dates.
The Critical Path Method (CPM) scheduling technique is used to calculate project schedules. CPM uses activity durations and relationships between activities to calculate the project schedule
How to Schedule? 
To Schedule the project press F9 key.

Select the data date and click on schedule command
P6 Schedules the project on CPM and Critical path activities will be displaced in red color
P6 Calculates early dates during Forward pass and Late Dates during Backward pass Calculation.
Difference between Late Finish and Early Finish is termed as
 Total Float 
Activities with Zero total Float are called as Critical Activities 
<<PREVIOUS                                                                  >>NEXT

Comments

  1. Mestre bom dia!

    Eu tenho um cronograma de colaboradores e preciso mudar os ícones do activity name da aparência do layout da janela, como faço isso!

    Já pesquisei e não achei em minhas pesquisas.

    No aguardo e muito obrigado!

    ReplyDelete

Post a Comment

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...