Adding Activities, Relationships and scheduling
Activities
are the Fundamental work elements of a project. They are the lowest level of a
work breakdown structure(WBS) and as such, are the smallest subdivision of a
project that directly concerns the project manager
You can define Following information for an activity
Activity ID and Name
Activity Calendars, Start and Finish Dates
Activity type, duration type, and percent complete type.
WBS element and Activity codes
Constraints
Expenses
Predecessor and successor relationships
Work Products and deliverables
Resource and Roles
You can define Following information for an activity
Activity ID and Name
Activity Calendars, Start and Finish Dates
Activity type, duration type, and percent complete type.
WBS element and Activity codes
Constraints
Expenses
Predecessor and successor relationships
Work Products and deliverables
Resource and Roles
Notes
and Feedback
Steps
Steps
•To Add Activities, Click on Activities in
the Home page or Project>Activities
•Organize Layout based on WBS & SORT
by Activity ID
•Add Activities to respective WBS Level by
clicking on ADD on command Bar button
1.Task
Dependent –> In a fixed duration
This
is the default activity type in P6.
2.Resource
Dependent
3.Level
of Effort
4.Start
Milestone
5.Finish
Milestone
6.WBS
summary
Activity Steps
Steps
allow you to break activities into smaller units and track the completion of
those units.
Activity % Complete type
The way in which the percent complete for the selected activity is determined
There
are 3 types in this
Duration
Type
Physical
Type
Units
Type
Relationships
A
Relationship defines how a Activity relates to the start or finish of another
activity. These Relationships form a logic to your project and are used
together for determining Schedule dates.
Relationship
Types
Finish
to Start (Default)
Finish
to Finish
Start
to Start
Start
to Finish
How to Assign Relationships?
•Select an Activity and select its
successor from “successor” tab in the activity detail form
•Activity details can be enabled from the
list of tool bars shown on the top of the layout.
Assigning Calendars and Activity codes
- To Assign Calendars/activity code select the activity and enable activity details
- In Activity details click on General/Codes Tab
- Click on Assign and select the respective calendar/codes.
Scheduling
Scheduling
can be done in two ways
When
you choose the schedule command or each time you make a change that affect
schedule dates.
The Critical Path Method (CPM)
scheduling technique is used to calculate project schedules. CPM uses activity
durations and relationships between activities to calculate the project
schedule
How to Schedule?
•To
Schedule the project press F9 key.
•Select
the data date and click on schedule command
•P6 Schedules the project on CPM and Critical path activities will be displaced in red color
•P6 Calculates early dates during Forward pass and Late Dates during Backward pass Calculation.
•Difference between Late Finish and Early Finish is termed as
Total Float
•Activities with Zero total Float are called as Critical Activities
<<PREVIOUS >>NEXT•P6 Schedules the project on CPM and Critical path activities will be displaced in red color
•P6 Calculates early dates during Forward pass and Late Dates during Backward pass Calculation.
•Difference between Late Finish and Early Finish is termed as
Total Float
•Activities with Zero total Float are called as Critical Activities
Mestre bom dia!
ReplyDeleteEu tenho um cronograma de colaboradores e preciso mudar os ícones do activity name da aparência do layout da janela, como faço isso!
Já pesquisei e não achei em minhas pesquisas.
No aguardo e muito obrigado!