Skip to main content

Primavera-1:5

Adding Activities, Relationships and scheduling 

Activities are the Fundamental work elements of a project. They are the lowest level of a work breakdown structure(WBS) and as such, are the smallest subdivision of a project that directly concerns the project manager 
You can define Following information for an activity 
Activity ID and Name
Activity Calendars, Start and Finish Dates
Activity type, duration type, and percent complete type.
WBS element and Activity codes
Constraints
Expenses
Predecessor and successor relationships
Work Products and deliverables
Resource and Roles
Notes and Feedback



Steps
To Add Activities, Click on Activities in the Home page or Project>Activities 
Organize Layout based on WBS & SORT by Activity ID 
Add Activities to respective WBS Level by clicking on ADD on command Bar button 

There are 6 types of Activity Types
 1.Task Dependent –> In a fixed duration
 This is the default activity type in P6.
 2.Resource Dependent
 3.Level of Effort
 4.Start Milestone
 5.Finish Milestone
 6.WBS summary

Activity Steps 

Steps allow you to break activities into smaller units and track the completion of those units.

Activity % Complete type 

The way in which the percent complete for the selected activity is determined 

There are 3 types in this 
Duration Type 
Physical Type 
Units Type

Relationships 

A Relationship defines how a Activity relates to the start or finish of another activity. These Relationships form a logic to your project and are used together for determining Schedule dates.

 Relationship Types

Finish to Start (Default)
Finish to Finish
Start to Start
Start to Finish
How to Assign Relationships?

Select an Activity and select its successor from “successor” tab in the activity detail form

Activity details can be enabled from the list of tool bars shown on the top of the layout.

Assigning Calendars and Activity codes

  • To Assign Calendars/activity code select the activity and enable activity details 
  • In Activity details click  on General/Codes Tab 
  • Click on Assign and select the respective calendar/codes.

Scheduling 

Scheduling can be done in two ways 
When you choose the schedule command or each time you make a change that affect schedule dates.
The Critical Path Method (CPM) scheduling technique is used to calculate project schedules. CPM uses activity durations and relationships between activities to calculate the project schedule
How to Schedule? 
To Schedule the project press F9 key.

Select the data date and click on schedule command
P6 Schedules the project on CPM and Critical path activities will be displaced in red color
P6 Calculates early dates during Forward pass and Late Dates during Backward pass Calculation.
Difference between Late Finish and Early Finish is termed as
 Total Float 
Activities with Zero total Float are called as Critical Activities 
<<PREVIOUS                                                                  >>NEXT

Comments

  1. Mestre bom dia!

    Eu tenho um cronograma de colaboradores e preciso mudar os ícones do activity name da aparência do layout da janela, como faço isso!

    Já pesquisei e não achei em minhas pesquisas.

    No aguardo e muito obrigado!

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Tutorial : Chapter 2.5 : Budgets

Budget Consists of quantities and cash flow required to complete a project. In the Planning stage project manager and other stakeholders need to estimate scope and budgets. As the scope changes, budget also needs to be adjusted to compensate. Primavera is helpful in establishing these budgets and tracking the changes in the budgets. In this Tutorial, let us learn how to establish budgets, establish monthly spending plans, implement changes to it and tracking monthly spending and variances right from EPS to Project and to WBS level. In the planning stage, we start the budgeting from the top level, like dividing the budget available to the EPS nodes for the duration of the projects. And then respective managers divide this budget to the projects for which they are responsible in each EPS node. Let us consider with an example here. Considering that we have $6000 allotted for an EPS node and it is having two projects and we divide this $6000 equally to these two projects as $3000 eac...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...