Skip to main content

Primavera-1:5

Adding Activities, Relationships and scheduling 

Activities are the Fundamental work elements of a project. They are the lowest level of a work breakdown structure(WBS) and as such, are the smallest subdivision of a project that directly concerns the project manager 
You can define Following information for an activity 
Activity ID and Name
Activity Calendars, Start and Finish Dates
Activity type, duration type, and percent complete type.
WBS element and Activity codes
Constraints
Expenses
Predecessor and successor relationships
Work Products and deliverables
Resource and Roles
Notes and Feedback



Steps
To Add Activities, Click on Activities in the Home page or Project>Activities 
Organize Layout based on WBS & SORT by Activity ID 
Add Activities to respective WBS Level by clicking on ADD on command Bar button 

There are 6 types of Activity Types
 1.Task Dependent –> In a fixed duration
 This is the default activity type in P6.
 2.Resource Dependent
 3.Level of Effort
 4.Start Milestone
 5.Finish Milestone
 6.WBS summary

Activity Steps 

Steps allow you to break activities into smaller units and track the completion of those units.

Activity % Complete type 

The way in which the percent complete for the selected activity is determined 

There are 3 types in this 
Duration Type 
Physical Type 
Units Type

Relationships 

A Relationship defines how a Activity relates to the start or finish of another activity. These Relationships form a logic to your project and are used together for determining Schedule dates.

 Relationship Types

Finish to Start (Default)
Finish to Finish
Start to Start
Start to Finish
How to Assign Relationships?

Select an Activity and select its successor from “successor” tab in the activity detail form

Activity details can be enabled from the list of tool bars shown on the top of the layout.

Assigning Calendars and Activity codes

  • To Assign Calendars/activity code select the activity and enable activity details 
  • In Activity details click  on General/Codes Tab 
  • Click on Assign and select the respective calendar/codes.

Scheduling 

Scheduling can be done in two ways 
When you choose the schedule command or each time you make a change that affect schedule dates.
The Critical Path Method (CPM) scheduling technique is used to calculate project schedules. CPM uses activity durations and relationships between activities to calculate the project schedule
How to Schedule? 
To Schedule the project press F9 key.

Select the data date and click on schedule command
P6 Schedules the project on CPM and Critical path activities will be displaced in red color
P6 Calculates early dates during Forward pass and Late Dates during Backward pass Calculation.
Difference between Late Finish and Early Finish is termed as
 Total Float 
Activities with Zero total Float are called as Critical Activities 
<<PREVIOUS                                                                  >>NEXT

Comments

  1. Mestre bom dia!

    Eu tenho um cronograma de colaboradores e preciso mudar os ícones do activity name da aparência do layout da janela, como faço isso!

    Já pesquisei e não achei em minhas pesquisas.

    No aguardo e muito obrigado!

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad