Lets learn How to Create a One Month filter in Primavera now
Now you can view the look ahead schedule as shown below
Step 1:
After Opening a Schedule in Primavera, click on the Filter Icon
Step 2:
After Clicking the Filter icon, you will get the following window as shown below, Click on New Button
Step 3:
Name the Filter as 1 Month Look ahead filter and Select in the Parameter Field as " Start" from the drop down menu
Step 4:
Step 5:
In the Value field, Select DD- Earliest Data DateStep 6:
In the High Value , type DD+1M,Step 7:
Then Click on ADD and In the Parameter field, Select Activity Status, in the Is field, select "is not equal to" , in the Value field, select "Completed" from the drop down menu. This is to list out the activities that are in progress as well as not started(excluding the completed activities). then Click "OK"Step 8:
Select the Filter (by clicking the check box beside the filter 1 month look ahead filter) and click on OK.Now you can view the look ahead schedule as shown below