How to Change the Calender in Primavera in the middle of the project

Hi, Lets see How we can change the Calendar once the schedule is prepared.
As per the Scheduling Philosophy, Calendar has to be set before beginning the schedule preparation.

To set the Default calendar,

Step 1:

Go to Enterprise>>Calendars,

Step 2:

Tick the Calendar which you want to make it default,

Step 3:

If you want to further change the timings and work weeks, click on Modify


Step 4:

Click on Work Weeks and Change the Time periods for the work hours in the default calendar

Step 5:

After Creating th Schedule, in the middle of the schedule, if you want to change the calendar  for the activities that you enter further, Go to Details tab>>Defaults Tab>>It will show the default calendar, if you want to change the calendar, select the calendar clicking the bubble.


Video as below


If you want to Change the Calendar of all the activities once the schedule is prepared, to see the impact of changing the calendars.

Step 1:

Open the project, Right Click on any activity and select Columns,

 Find (Ctrl+F) and type in Calendar and select the calendar, and click on OK
- To insert the calendar column.



Step 2:

Select the top most cell in the calendar column and press the Shift key on the keyboard and Select the bottom most cell of the Calendar column, right click and select the Fill down option- to change the calendars for all the activities of the schedule.




Doing this, the default calendar will be shown only for the WBS,but the calendars for the activities get changed.

Video :

Back to Primavera>>

Comments

  1. Thanks! You’re great!” & it was Great share!!! with detailed research once again thanks for it. The Shift Calendar control the Price/Unit for activity, depend on what time activity start and finish. we can choose from many dedicated software (like primavera P6 tool) Best Primavera Training
    MS Project Training

    ReplyDelete
  2. I guess when the no of activities will be large global change will be a much better option.

    ReplyDelete
  3. It was Great share!!! with detailed research. You have mentioned easy steps to set calendar before beginning the schedule preparation.
    Project Management Collaboration Tools
    Project Management Scheduling Software

    ReplyDelete
  4. It was nice to learn about Time Tracking Software from your post. Reading this blog is quite interesting and relevant.

    Visit: Time Tracking Software

    ReplyDelete
  5. This was an authentic and useful piece of information. Thank you for giving this useful content.
    Phases Of Hacking
    Steps Of Hacking

    ReplyDelete
  6. very helpful content about primavera project, I learned a lot from this article, please keep us up to date

    ReplyDelete

Post a Comment

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...