How to Change the Calender in Primavera in the middle of the project

Hi, Lets see How we can change the Calendar once the schedule is prepared.
As per the Scheduling Philosophy, Calendar has to be set before beginning the schedule preparation.

To set the Default calendar,

Step 1:

Go to Enterprise>>Calendars,

Step 2:

Tick the Calendar which you want to make it default,

Step 3:

If you want to further change the timings and work weeks, click on Modify


Step 4:

Click on Work Weeks and Change the Time periods for the work hours in the default calendar

Step 5:

After Creating th Schedule, in the middle of the schedule, if you want to change the calendar  for the activities that you enter further, Go to Details tab>>Defaults Tab>>It will show the default calendar, if you want to change the calendar, select the calendar clicking the bubble.


Video as below


If you want to Change the Calendar of all the activities once the schedule is prepared, to see the impact of changing the calendars.

Step 1:

Open the project, Right Click on any activity and select Columns,

 Find (Ctrl+F) and type in Calendar and select the calendar, and click on OK
- To insert the calendar column.



Step 2:

Select the top most cell in the calendar column and press the Shift key on the keyboard and Select the bottom most cell of the Calendar column, right click and select the Fill down option- to change the calendars for all the activities of the schedule.




Doing this, the default calendar will be shown only for the WBS,but the calendars for the activities get changed.

Video :

Back to Primavera>>

Comments

  1. Thanks! You’re great!” & it was Great share!!! with detailed research once again thanks for it. The Shift Calendar control the Price/Unit for activity, depend on what time activity start and finish. we can choose from many dedicated software (like primavera P6 tool) Best Primavera Training
    MS Project Training

    ReplyDelete
  2. I guess when the no of activities will be large global change will be a much better option.

    ReplyDelete
  3. It was Great share!!! with detailed research. You have mentioned easy steps to set calendar before beginning the schedule preparation.
    Project Management Collaboration Tools
    Project Management Scheduling Software

    ReplyDelete
  4. It was nice to learn about Time Tracking Software from your post. Reading this blog is quite interesting and relevant.

    Visit: Time Tracking Software

    ReplyDelete
  5. This was an authentic and useful piece of information. Thank you for giving this useful content.
    Phases Of Hacking
    Steps Of Hacking

    ReplyDelete
  6. very helpful content about primavera project, I learned a lot from this article, please keep us up to date

    ReplyDelete
  7. Thank you for this blog. Java Online Course
    Java Training in Bangalore
    It is very informative.

    ReplyDelete

Post a Comment

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...