Skip to main content

How to Change the Calender in Primavera in the middle of the project

Hi, Lets see How we can change the Calendar once the schedule is prepared.
As per the Scheduling Philosophy, Calendar has to be set before beginning the schedule preparation.

To set the Default calendar,

Step 1:

Go to Enterprise>>Calendars,

Step 2:

Tick the Calendar which you want to make it default,

Step 3:

If you want to further change the timings and work weeks, click on Modify


Step 4:

Click on Work Weeks and Change the Time periods for the work hours in the default calendar

Step 5:

After Creating th Schedule, in the middle of the schedule, if you want to change the calendar  for the activities that you enter further, Go to Details tab>>Defaults Tab>>It will show the default calendar, if you want to change the calendar, select the calendar clicking the bubble.


Video as below


If you want to Change the Calendar of all the activities once the schedule is prepared, to see the impact of changing the calendars.

Step 1:

Open the project, Right Click on any activity and select Columns,

 Find (Ctrl+F) and type in Calendar and select the calendar, and click on OK
- To insert the calendar column.



Step 2:

Select the top most cell in the calendar column and press the Shift key on the keyboard and Select the bottom most cell of the Calendar column, right click and select the Fill down option- to change the calendars for all the activities of the schedule.




Doing this, the default calendar will be shown only for the WBS,but the calendars for the activities get changed.

Video :

Back to Primavera>>

Comments

  1. Thanks! You’re great!” & it was Great share!!! with detailed research once again thanks for it. The Shift Calendar control the Price/Unit for activity, depend on what time activity start and finish. we can choose from many dedicated software (like primavera P6 tool) Best Primavera Training
    MS Project Training

    ReplyDelete
  2. I guess when the no of activities will be large global change will be a much better option.

    ReplyDelete
  3. It was Great share!!! with detailed research. You have mentioned easy steps to set calendar before beginning the schedule preparation.
    Project Management Collaboration Tools
    Project Management Scheduling Software

    ReplyDelete
  4. It was nice to learn about Time Tracking Software from your post. Reading this blog is quite interesting and relevant.

    Visit: Time Tracking Software

    ReplyDelete
  5. This was an authentic and useful piece of information. Thank you for giving this useful content.
    Phases Of Hacking
    Steps Of Hacking

    ReplyDelete
  6. very helpful content about primavera project, I learned a lot from this article, please keep us up to date

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

Primavera P6 Tutorial : Chapter 2.5 : Budgets

Budget Consists of quantities and cash flow required to complete a project. In the Planning stage project manager and other stakeholders need to estimate scope and budgets. As the scope changes, budget also needs to be adjusted to compensate. Primavera is helpful in establishing these budgets and tracking the changes in the budgets. In this Tutorial, let us learn how to establish budgets, establish monthly spending plans, implement changes to it and tracking monthly spending and variances right from EPS to Project and to WBS level. In the planning stage, we start the budgeting from the top level, like dividing the budget available to the EPS nodes for the duration of the projects. And then respective managers divide this budget to the projects for which they are responsible in each EPS node. Let us consider with an example here. Considering that we have $6000 allotted for an EPS node and it is having two projects and we divide this $6000 equally to these two projects as $3000 eac...