How to Import a Microsoft Project Schedule into Primavera With Same dates

Let us now learn How to Import a Microsoft Project Schedule into Primavera with the same dates exiting in the Microsoft project

Primavera have the option of Importing the schedules which are in the following formats.


If we directly import from Microsoft project in the .MPP format by default. The dates may differ from the Microsoft Project when the calendars in the two formats are different. So, As to Eradicate this issue, there is a best way of importing. It's Simple. First we have to convert the MSP file to .XML format and then import the .xml  format in to primavera and see that the dates wont get changed. It'a very helpful tool for those who work on two platforms.

Step 1:

Open the Schedule in the Microsoft Project and save it in the Microsoft .XML format.



Step 2:

Open Primavera Now and Go to File>>Import>>
In the Import Format window,  Select the Last Option Microsoft and in the drop down menu select the .XML format and Click on Next Button

Step 3:

In the files to Import Window, Click on Select Button and Browse the .XML File,




Step 4: 

In the "Import to" column click and select the EPS where you would like to place the project and Click on Next  Button

Step 5:

And click on the Finish Button, If you are ready to import in the Import Confirmation Window

Step 6:

Then after importing, you will be displayed with a successful importing message. Click on the Close Button

 An Find the Desired Project in the desired EPS location, Now you have your Microsoft Schedule in the Primavera with the same dates.

See the Detail demo of the same in the Below Video


Back to Primavera>>

Comments

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...