Primavera P6 Tutorial : Chapter 2.5 : Budgets

Budget Consists of quantities and cash flow required to complete a project. In the Planning stage project manager and other stakeholders need to estimate scope and budgets. As the scope changes, budget also needs to be adjusted to compensate. Primavera is helpful in establishing these budgets and tracking the changes in the budgets.
In this Tutorial, let us learn how to establish budgets, establish monthly spending plans, implement changes to it and tracking monthly spending and variances right from EPS to Project and to WBS level.
In the planning stage, we start the budgeting from the top level, like dividing the budget available to the EPS nodes for the duration of the projects. And then respective managers divide this budget to the projects for which they are responsible in each EPS node. Let us consider with an example here. Considering that we have $6000 allotted for an EPS node and it is having two projects and we divide this $6000 equally to these two projects as $3000 each.
LevelBudget Allotted
EPS Node$6000
Project – 1$3000
Project - 2$3000
Once the budgeting is done at the EPS nodes, and then distributing them to the next level of projects, you need to establish a spending plan to keep track of cash flows for each EPS node and Project.
You can establish budget estimates at the planning stage, then refine them as projects progress
Establishing Budgets:
For Establishing Budgets, Go to the Projects window. Select the EPS Node, here for example let us consider EPS node “SAMPLE”, go to the details in the bottom of the window and choose “Budget Log” tab, enter the total budgeted amount you anticipate for this EPS in the Original Budget field as “$6000”.

After you have entered budgeted totals for an EPS node, distribute this budget to the projects present in this EPS node. As we have allotted $6000 to the EPS node, let us distribute this budget into $3000 each for the two projects present. Enter the Budgeted amount in the Original Budget field as “$3000”

Monthly Spending Plan:
After you have entered budgeted totals for a node and its projects, you can start apportioning anticipated monthly spending amounts for the EPS node and subsequently to each of the projects in the EPS branch. In this example as we have got the project timeline from Feb’16 to Apr’16, let us go to the “Spending Plan” tab in the details section and distribute $6000 as $2000 for each month in the EPS node and $1000 for each month for both the projects in the EPS Branch.

And similarly allocate $1000 for each month for both the projects in the EPS Branch as shown in the below picture.

Now let us go the project “Sample-1” and allocate this budget to the WBS Level also. Open the project and go to WBS Window.

After opening the project. In this example, as we have allotted $3000 for the project and let us assume we have 3 WBS Elements and we distribute $1000 for each WBS Element. Enter the $1000 for each WBS Element’s Original budget field in the “Budget log” Tab as shown below.

Click the Spending Plan tab in the WBS window. Enter total expenditures for each month in the Spending Plan column for all the WBS Elements. In this example, it is as shown in the below table.
LevelBudget allottedFeb’16Mar’’16Apr’16
Project$3000$1000$1000$1000
   WBS-1   $1000   $250   $250   $250
   WBS-2   $1000   $250   $500   $500
   WBS-3   $1000   $750   $500   $500
‘=1+2+3’Total Spending Tally $1250 $1250 $1250
Enter into the Spending Plan Tab like shown in the below figure for all the WBS Elements, with the figures shown in the above table. There is no need that we have to allocate only the budget allotted for the WBS node, the actual figures may differ at the monthly spending plans as per the revised planning of the manager involved.

After you are done with this, there is another column “Spending Plan Rally”. The Spending Plan Tally column shows any amounts previously recorded for project spending plans (summation of all the budgets planned for the particular month.). Now go to the Project node “Sample-1” which is root WBS and observe that the spending plan tally is the summation of all the spending plans of the WBS Elements. And the excess amount that has been planned at the WBS elements appears in red ($250 in this example) in the Undistributed Current Variance column as shown in the below figure.


Tracking Budget Changes

As projects progress, changes in scope, resources allocation, funding /withdrawals affects original budgeted amounts. The Budget Change Log available here in Primavera enables you to track modifications that affect the budget; this log also provides a clear indication of the reason for the change in the budget, by this you can maintain a log of all budget changes into categories like approved, pending, not approved.
Approved budget will be added into the current budget and the rest will be shown as the proposed budget.
Only authorized project participants may issue budget changes and mark them as approved.
As per the user access and privileges allotted, you may post a change amount as Pending; the program manager of the affected EPS node, or the project manager of the affected project, must then mark the amount as Approved or Not Approved. And the Module calculates the proposed budget and current budget as per the logic mentioned.
Proposed Budget = Original Budget + (approved + pending) Budget Changes
Current Budget = Original Budget + Approved Budget Changes
Picture shown below is a snapshot on how to add the budget log and mention the status in the respective fields.

Click the Budget Summary tab to track budget and spending totals as projects progress. The Budget Summary tab enables you to see all the details like current budget, unallocated budget, distributed current budget, Variances spending plans and benefit plans.  This would project all the summary details of your project’s financial status.

Funding Sources:

Projects are generally funded by sources outside or within your organization. So you can set up a database of your funding sources, from which you can easily assign the funding sources to the projects or WBS elements as and when required.
To Define Funding Sources, Go to Menu bar, Choose Enterprise, click on “Funding Sources

Select the funding source immediately above and at the same level as the fund you want to add, then click Add. And then maintain your own funding sources dictionary. Type any additional information about the funding source in the description area as shown below.

Tracking and Analyzing Budgets

At the EPS level / Project level, you can customize columns and produce reports to display original budget amounts along with the current variance amounts. This is beneficial in the early stages of your projects to track and analyze your budget changes for all the projects available.
Once you are done with the perfect view of columns, you can save the layout for further future reference, which reduces and save a lot of time.
To create a layout: Open the Projects window, then click the Display Options bar and choose Columns, Customize. You can select any budget-related columns from the list of choices like original budget, current variances columns.

Here is the illustrative video tutorial of the same for your better understanding
[paypal_donation_button align="center"]

Comments


  1. Tag: PM203A53. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

    1. Plan your day using time management techniques

    As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

    If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

    Related post: Free ebook 104 secrets to become a great project manager

    2. Include stakeholders in important project conversations

    While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

    Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

    Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

    3. Regularly communicate with your team

    Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

    For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

    4. Anticipate project setbacks

    Even the best-laid plans often go awry.

    Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

    Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

    Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

    Related post: 92 free project management templates

    5. Stay focused on the details

    A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

    Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

    And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs



    ReplyDelete
  2. I want to thank you for this wonderful article!! This article gives us exact knowledge about Productivity and monitoring software. And I also published a similar article about monitoring software I hope you visit here and get something good related to Productivity.



    Visit here :- Productivity Monitoring Software

    ReplyDelete
  3. P6 Professional can be used to organize projects up to 100,000 activities, and it provides unlimited resources and an unlimited number of target plans. Massive data requires sophisticated yet highly flexible organization tools to provide you a multitude of ways to organize, filter and sort activities, projects, and resources.

    ReplyDelete
  4. Primavera P6 EPPM is web–based and easy to use. You can quickly add new users by just providing a login. There is no installation needed on a local PC. Yes, P6 EPPM offers richer graphics and dashboards, but this software is geared towards the enterprise demands for portfolio management and multi-project environments.

    ReplyDelete
  5. hi Mr!
    I read this blog of yours in which you mentioned the Tracking and Analyzing Budgets I have learned a lot of knowledge from it
    <a href="https://burraq.org/primavera-p6-training-in-lahore/>Primavera Training</a>

    ReplyDelete
  6. I'm really impressed with your writing skills, as smart as the structure of your


    Latest Software Free Download



    weblog. Is this a paid topic



    Mediacoder crack



    do you change it yourself? However, stopping by with great quality writing, it's hard to see any good blog today.



    Push video wallpaper -crack





    Iobit start menu -crack





    Pinnacle pro -crack



    abyssmedia audio pro crack

    ReplyDelete
  7. Thanks and I have a super offer: What Is House Renovation houses to renovation

    ReplyDelete

Post a Comment

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...