Skip to main content

Primavera P6 Tutorial : Chapter 2.6 : Project Codes

You can organize the Projects in EPS in groups according to categories such as location wise, discipline wise using the project codes.
Using Project codes, you can arrange projects hierarchically when your EPS have many projects with many levels.
You can establish as many as project codes to meet the grouping, sorting, filtering and reporting requirements for your projects.
In this Chapter, let us see how to establish the project codes, assign them to projects and use them to organize the layouts.

Establishing Project Codes:

To define Project codes, go to Menu bar, Choose Enterprise, Project Codes.

Click Modify in the Project Codes dialog box, then add to define as many project code definitions as you need.

Click Modify, then type a project code name, along with the number of characters that will be available for each code value.

In the Project Codes dialog box, select the project code for which you want to establish values, then click Add and type the values and descriptions. To change a code value’s position in the project codes hierarchy, select the code, then click the arrow button.

To see a graphical display of your project codes hierarchy, click the Display Options bar and choose Chart View


You can also modify the appearance of the charts by right clicking the mouse and select on customize tab.

The Project Management module works with the weighted project codes, enabling you to rank or prioritize projects using a weight value and then view projects by score. For example, assume you rank projects in terms of priority. Project codes with the highest score have the most priority; those with the lowest score have the least priority.
To add Weights to a project code:
Click the Display Options bar, select Columns, then choose Weight.

And then enter a value in the Weight column for each project code in this dialog box.

Assigning Project codes to Projects:

In the Projects window, select a project. In the details tab at the bottom click the Codes tab.

Then click Assign. In the Assign Project Codes dialog box, click the value for the applicable code

Then click the Assign button (+).

Grouping, Sorting and Filtering by Codes:

Use project codes to group projects in Activity Table and Gantt chart layouts within the Projects window.
Right click on the project’s window, then choose Group and Sort By. Choose a specific project code or choose Customize to include additional codes or other project elements in your layout.

To Filter:
You can create custom filters that use project codes to limit the view of projects that are included in the Projects window. In the menu bar, choose Filter By

Customize. Click “New” in the Filters dialog box to add a filter.

Name the Filter name and mention the rules which it has to filter and click OK.
The new filter is listed under User Defined filters, and the corresponding select checkbox is marked, indicating it is active. Click Apply or OK to see the projects selected by the filter.

Here is an Illustrative video tutorial of the same for better understanding:
[paypal_donation_button align="center"]

Comments

Post a Comment

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...