Skip to main content

Primavera P6 Tutorial : Chapter 2.4 : Work Breakdown Structure (WBS)

A work breakdown structure (WBS) is a hierarchical arrangement of the services required during a project. The project is the highest level of the WBS while an individual activity or service is the lowest level. Each project in the enterprise project structure (EPS) will be further breakdown into WBS for better management.
During the planning stage, Project Manager typically develops the WBS first,
WBS can be created up to 50 levels. Maximum character length for any WBS Code is 20 and for WBS Name are 100.
In this Chapter, we will learn how to set up and how to implement a Work Breakdown Structure (WBS)

The Work Breakdown Structure (WBS)

Beyond the EPS, we have Projects and each project will be further divided into WBS. Open the EPS element, open any Project in it and click on WBS from the directory bar.
Viewing WBS:
Go to Menu Bar, Choose Project and Select WBS; you can also click WBS from the Directory bar or from the Home workspace.

You can view a WBS as a chart or a table. Click the Display Options bar, then choose Show on Top, Chart View.

If you select the Chart View, it will be displayed as shown in the below figure.

To change the displayed information, click the Display Options bar and choose Chart Box Template, then select the information type, which you would like to customize.

If you would like to view the WBS as a Standard table, Click the Display Options bar, then choose Show on Top, WBS Table.
You can also choose to display a Gantt chart to the right of the WBS table. Click the Display Options bar, choose Show on Top and select Gantt chart.
To view detailed information about a specific WBS element, choose Show on Bottom, WBS Details, then select the WBS element whose information you want to view. To hide WBS Details, choose Show on Bottom, No Bottom Layout.
You can customize the columns in the WBS Display, choose columns, then click customize the columns. Add the columns that you prefer and you can then save this settings as a layout even for future viewing as per the requirement.
\


Grouping by WBS:
Group by WBS path in the Activities and WBS windows, you can also filter or display the WBS path as a column in projects.

You can do this as well from the activities window: Choose Project, Activities, then choose View, Group and Sort.
In the Group By section, click the cell, then select WBS Path. Click Sort, then select a sort order for the WBS path. Click OK.

Adding WBS Elements
Choose Project, select WBS. Select the WBS element immediately above and under which you want to add the new element, then click Add. The new WBS element is indented one level under the selected WBS element.

Use the arrows in the Command Bar to indent the WBS Element that has been added.

Display Work Breakdown Structure Details by clicking the Display Options bar, choosing Show on Bottom, and select WBS Details.

Use the General tab to view and edit the selected WBS element’s general details. This includes the WBS code, WBS name, status and responsible manager. Anticipated dates also can be mentioned in the right side of the tab.

WBS Element’s Status
There are four status types for WBS elements: Active, Inactive, Planned and What-If.

Active WBS elements
If a WBS element’s status is Active, Progress Reporter users can view all activities included in this WBS element. Users may also be able to assign themselves to and perform work on activities that are included in this Active WBS element.
Inactive WBS elements
If a WBS element’s status is Inactive, depending on the project level setting on the Project Details Resources tab, Progress Reporter users can view activities that belong to the WBS. When this option is turned on, Progress Reporter users can view, but cannot edit activities that are included in the Inactive WBS element.
Planned WBS elements
If a WBS element’s status is Planned, Progress Reporter users cannot view any activities included in this WBS element. This prevents Progress Reporter users from assigning themselves to and performing work on activities assigned to this WBS element that is not authorized for actual use.
What-If WBS elements
If a WBS element’s status is What-If, Progress Reporter users cannot view any activities included in the WBS element. If a WBS element belongs to a higher-level WBS element, both elements have the same status.
WBS Milestones
In the initial stages of project planning, one has to decide how the PM module will calculate earned value, percent complete, and resource use. To this, you can add an unlimited number of WBS milestones, which can also be used to calculate earned value.

Milestones are assigned at the WBS level, and each milestone is given a weightage that indicates its importance to the project. When you mark a WBS milestone as complete, the module uses its weightage to calculate the performance percent completion of all activities included in that WBS level.
Estimation Weights to WBS Milestones
Use the WBS Milestones tab to add an unlimited number of WBS milestones to a WBS element. Click Add, then type a name for the milestone and assign a weight for calculating performance percent complete for all activities in the WBS element.

For Example, as shown in below figure, let us consider four WBS milestones for a WBS Element with equal weightage as 1 each. And now when you update one of the milestone as Completed, it calculates the % completion as 25%.

If this same milestone had a weight of 9.0, and the other three had 1.0 weights, marking it Completed would indicate that the WBS element is 75% complete.

The module uses the following formula to calculate percent complete from weighted milestones:
= Actual Weight of Completed Milestones / Total Weight of All Milestones
 WBS Category Values
You can define a custom category and category values for WBS elements. This category and its values also enables you to group, sort, and filter WBS elements.
Choose Project, WBS. Add the WBS category “Project Phase” as a column by clicking the Display Options bar and choosing Columns, Customize.

Select the WBS element to which you want to assign a category value, then click the Browse button in the WBS category column.

Earned Value Settings
Earned value is a technique for measuring project performance according to both project costs and the project schedule, comparing the budgeted cost of the work to the actual cost.
You can use the Earned Value tab in Work Breakdown Structure Details to specify settings for calculating the selected WBS element’s earned value.
Earned Value = Budget at Completion (BAC) x Performance % Complete
To Define: Select the WBS element for which you want to define earned value settings, then click the Earned Value tab.

For Technique for Computing the Performance percent complete, select any of the following:
Activity Percent Complete: Calculates earned value according to current activity completion percentages and the percent complete type selected on the General tab of Activity Details.
Use resource curves / future period buckets: Overrides the Activity Percent Complete type for activities that have a resource curve assigned. If a curve is assigned, Units Percent Complete is always multiplied by the Budget at Completion to calculate Earned Value.
WBS Milestones Percent Complete: Calculates earned value according to completion of the WBS element’s weighted milestones,
0/100 Percent Complete: Calculates earned value as 100 percent only after the activity ends.
50/50 Percent Complete: Calculates earned value as 50 percent after the activity starts and until the activity ends.
Custom Percent Complete: Calculates earned value as a percentage you specify.
For Technique for Computing the Estimate to complete (ETC), select any of the following:
ETC = Remaining Cost for Activity: Calculates ETC values as the remaining cost to complete an activity
PF = 1: Calculates ETC values as Budget at Completion (BAC) - Earned Value Cost. This method yields an optimistic result.
PF = 1/CPI: 1 divided by the Cost Performance Index (CPI).This method yields the most likely result.
PF = 1/ (CPI*SPI): 1 divided by the product of the Cost Performance Index (CPI) and Schedule Performance Index (SPI). This method yields a pessimistic result.
PF =: Calculates ETC values according to a PF you specify
Here is the illustrative video tutorial of the same for your better understanding

Comments


  1. Tag: PM203A52. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

    1. Plan your day using time management techniques

    As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

    If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

    Related post: Free ebook 104 secrets to become a great project manager

    2. Include stakeholders in important project conversations

    While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

    Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

    Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

    3. Regularly communicate with your team

    Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

    For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

    4. Anticipate project setbacks

    Even the best-laid plans often go awry.

    Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

    Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

    Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

    Related post: 92 free project management templates

    5. Stay focused on the details

    A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

    Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

    And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs



    ReplyDelete
  2. This information is impressive; I am inspired by your post writing style & how continuously you describe this topic. After reading your post, thanks for taking the time to discuss this, I feel happy about it and I love learning more about this topic.

    primavera training in chennai

    ReplyDelete
  3. Thanks for your informative article. Softlogic Helo you to get the EXCEL TRAINING WITH PLACMENT IN CHENNAI. More Details Visit the Link

    ReplyDelete
  4. THANKS FOR SHARING SUCH A AMAZING WORK
    NICE WORK
    Project Management UK

    ReplyDelete
  5. "I loved the post, keep posting interesting posts. I will be a regular reader...

    rent car islamabad

    ReplyDelete
  6. "I loved the post, keep posting interesting posts. I will be a regular reader...

    seomagician.co.uk

    ReplyDelete
  7. Simply wish to say your article is as astonishing. The clarity in your post is simply great, and I could assume you are an expert on this subject. Well with your permission let me grab your RSS feed to keep updated with forthcoming post. Thanks a million and please keep up the gratifying work.

    Project Management Apps

    ReplyDelete
  8. WBS Schedule Pro
    I am very impressed with your post because this post is very beneficial for me

    ReplyDelete

  9. Thanks for watching this video, if you want to download the latest version of this software.
    SO the link is given below!!!
    piratelink.org
    WBS Schedule Pro Crack

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad