Skip to main content

Primavera P6 Tutorial : Chapter 2.8 : Calendars

The calendars define the number of available work hours in each calendar day. You can then create and assign calendars to each resource and each activity. The Primavera module uses your calendar for scheduling and tracking activities, and also leveling resources across your organization. You can link resource and project calendars to global calendars.
In this Chapter, let us learn how to add calendars and how to modify them.

Add Calendars:

You can create an unlimited number of calendars to accommodate different work patterns in your organization. You can create different calendars and assign the activities and resources in your projects to them.
Basically there are three calendar pools: Global, Resource, and Project.

The global calendar pool contains calendars that apply to all projects in the database.
The resource calendar pool is a pool of calendars for each resource.
The project calendar pool is a pool of calendars for each project in the organization.
You can assign either of the resource or global calendars to resources, and either of the global or project calendars to activities.
To Create Calendar:
Go to Menu bar, Choose Enterprise, Calendars. Choose Global, then click Add.















Select the calendar you want to copy for the new global calendar, then click the Select button

Type the new calendar’s name. To edit the new calendar, click Modify.

To view the calendar’s assignments before changing it, click Used By.

Follow the same procedure for adding the resource or project calendar. Only difference is that you must first open a project, when creating a project calendar.
Use more than one calendar when your projects contain activities that can occur on different schedules. The Primavera module schedules each activity only during the work times of the calendar to which it is assigned.

Modify Calendars:

To modify: Go to Menu Bar, Choose Enterprise, Calendars; choose the calendar type (Global, Resource, or Project), select the calendar you want to modify, then click Modify.
To change the number of hours in a specific workday, click the date you want to change and edit the work-hours /day.

To Specify default work hours:
In the calendar dialog box, click Workweek. Use the Calendar Weekly Hours dialog box to specify the number of default work hours for each week day in the open calendar.

If we edit the existing calendar and change the Saturday’s work hours as non-working, the color will be changed as shown in the below figure.

To Define default hours per time period:
In the calendar dialog box, click Time Periods and define the calendar's default number of hours per time period.

If you click the detailed work hours per day. You can either click to make the selected hour a work hour or click to make the selected hour a non-work hour.

You can set preferences to display time units in increments such as Hour, Day, Week, and Month. This can be done by going to Edit>>User Preferences

Administrators can define Hours per Time Period settings globally on the Admin Preferences, Time Periods tab, or they can specify that the Hours per Time Period settings should be defined per calendar.

Here is an Illustrative video tutorial of the same for better understanding:
[paypal_donation_button align="center"]

Comments

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad