Skip to main content

Primavera P6 Tutorial : Chapter 4.2 : Assigning Baselines

You can use the assign baselines feature to designate the current project or an existing baseline as the project, primary, secondary, or tertiary baseline. The project baseline or primary baseline can be designated as the project to use when calculating earned value

Assigning Baselines:

Open the project for which you want to select a project baseline. Go to Menu bar, Choose Project, Assign Baselines.

The primary, secondary, and tertiary baselines are user-defined baselines used to compare projects.

In the Project field: select the project to which you want to assign a project baseline.
In the Project Baseline field: select the desired baseline or the current project. If no baseline is designated as active, the current project is used as the baseline project.

Under User Baselines, choose an existing baseline or the current project.as the primary, secondary or tertiary baseline for a project from the drop down menu. You can compare up to 3 baselines at a single time, you can assign the same project as secondary and tertiary baselines.

Comparison with Baseline Schedules:

Open a layout showing current and baseline bars to identify tasks that start or finish later than planned. You can even modify the layout suiting your requirement for better comparison and save the layout for later usage, makes it easy to see variances between the current and baseline dates.

We have a pre-defined global layout for comparing the current schedule with the baseline called “Baseline comparison

Add columns in the Activity Table for almost any data particular from the baseline project.

Right click on the gantt area and choose bars to represent and format baseline dates/fields.


Preferences of Earned Value calculations:

Select a Project and go to project details and then settings tab, choose to calculate earned value using the project baseline or the baseline you have defined as your primary baseline.

Earned Value Calculation settings:
To specify how earned value is calculated, choose Admin, Admin Preferences.

On the Earned Value tab, in the Earned Value Calculation section, choose to calculate earned value from a baseline using At Completion values with current dates, Budgeted values with current dates, or Budgeted values with planned dates from the drop down menu.

Here is the detailed video tutorial for your better understanding:

[paypal_donation_button align="center"]

Comments

Post a Comment

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...