How To Use Level Of Effort Activity In Primavera P6 To Summarize Schedules || LOE Definition



How To Use Level Of Effort Activity In Primavera P6 To Summarize Schedules || LOE Definition

Level of Effort activities are an essential component in building complete schedules, for displaying and representing supportive, non-discrete work.

Examples of Level of Effort activities include: 
Customer Meetings, Project Management, Site Management tasks, Maintenance of equipment Clerical work,

In this tutorial, let us consider a small sample project with 7 activities from Start to Finish and with 5 more activities

In this example, let us add an activity called as Project Management and put the type of activity as Level of Effort in the activity details.

And then link it with the predecessor as Start activity with Start-Start relationship and successor as Finish activity with the Finish-Finish relationship.

When you schedule by pressing F9, you will notice that the LOE activity's duration and dates change accordingly with the relationships given.

Observe one more point here, even though this LOE activity is on the longest path, this will be not on the critical path.

So, by this, you should understand that the LOE activities will not add any duration to the project, but would be helpful in summarizing the group of activities.

You can even assign resources to the LOE activity to see the resources spread over the duration.
Let me assign carpenter resource by going into the resources tab.

So, this way you can use level of effort activity to summarize activities as per your requirement in Primavera P6.

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Comments

  1. PMP CERTIFICATION COURSE


    The PMP course provides managers with the latest information on Project Management norms and practices.Click here to know more
    pmp certification course

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...