Skip to main content

How To Use Level Of Effort Activity In Primavera P6 To Summarize Schedules || LOE Definition



How To Use Level Of Effort Activity In Primavera P6 To Summarize Schedules || LOE Definition

Level of Effort activities are an essential component in building complete schedules, for displaying and representing supportive, non-discrete work.

Examples of Level of Effort activities include: 
Customer Meetings, Project Management, Site Management tasks, Maintenance of equipment Clerical work,

In this tutorial, let us consider a small sample project with 7 activities from Start to Finish and with 5 more activities

In this example, let us add an activity called as Project Management and put the type of activity as Level of Effort in the activity details.

And then link it with the predecessor as Start activity with Start-Start relationship and successor as Finish activity with the Finish-Finish relationship.

When you schedule by pressing F9, you will notice that the LOE activity's duration and dates change accordingly with the relationships given.

Observe one more point here, even though this LOE activity is on the longest path, this will be not on the critical path.

So, by this, you should understand that the LOE activities will not add any duration to the project, but would be helpful in summarizing the group of activities.

You can even assign resources to the LOE activity to see the resources spread over the duration.
Let me assign carpenter resource by going into the resources tab.

So, this way you can use level of effort activity to summarize activities as per your requirement in Primavera P6.

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Comments

  1. PMP CERTIFICATION COURSE


    The PMP course provides managers with the latest information on Project Management norms and practices.Click here to know more
    pmp certification course

    ReplyDelete

Post a Comment

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animat...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...