You know that in Primavera we can work with multiple projects simultaneously at the same time. when we open 2 projects, by default Primavera show 2 critical paths, as each project will have its own critical path.
What if? we want to show only 1 critical path for the program consisting of two projects.
Let us see this in detail in this tutorial.
Click F9 or schedule icon and click on Options In general tab, under “Calculate float based on finish date of”. Check on “Opened projects” rather than each project Click Close and click on schedule button to run Schedule.
Now we can see Primavera display only 1 critical path, you can see the bars in red.
This critical path is being calculated based on the Finish date of Project 2 to calculate the Total Float.
So friends, in this way you can display only one critical path with multiple projects opened in Primavera P6.
For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.
***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************
You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh
Comments
Post a Comment