Skip to main content

How to Change Calendar From 5 Day to 7 Day but keep Project Finish Date Unchanged In Primavera P6


In this tutorial, let us learn how to change the calendar from 5-day workweek to 7-day work week but keeping the project finish Date unchanged in Primavera P6.

After working for so many hours to complete the project schedule, you might be getting to know that you should be using the 7-day calendar instead of the 5-day calendar.

Changing Activity calendar will change everything. Normally, if we change the calendar to 7 Day Workweek, all the activity finish dates will change.

Now the sample project in this video is having the finish date as 21st Oct’19 And now, if you change the calendar to the 7-day workweek, the Project finish date will be changing to 03rd Jul’19.

So, in this tutorial, I will show you How to Change Calendar from 5 Day Workweek to 7 Day Workweek but keeping Project Finish Date unchanged.

In the original schedule
Step 1: Go to menu bar and under Enterprise tab, choose User Defined Fields Create a field with the title “Finish 5D” and Data Type as Finish Date. And one more user-defined field with the title “Start 5D” with Data Type as Start Date

Step 2: Go to menu bar and under Tools tab, choose Global Change.
Create a global change and name it as “SaveTo5D” and create the rule as if where “blank”, then Start5D= Planned Start date, Finish5D=Planned Finish date and
click “Change” button to copy value to “Start 5D” and “Finish 5D” UDF and then click on commit changes, close the window

Step 3: Now Change Activity calendar to 7 Day Workweek. You can change the calendar for the first activity then use Fill Down function to apply for the rest activities.

Step 4: Go to menu bar and under Tools tab, choose again the Global Change. Create a Change “Copyfrom5D” and set the rules as If where “blank”, then Planned Start date = Start5D, Project Finish date = Finish5D.

Click “Change” button to copy the value to Start and Finish date.

Now we can see all activity Start and Finish date doesn’t change, only the Activity Duration changes.
You can observe that the Project finish Date is still 21-Oct-19.

So friends, in this way one can change the calendar without changing the Project Finish Date.

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Comments

  1. it`s work if you have a relationship without a lag.but if you have a lag this is the problem

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad