Skip to main content

Best Way To Show All Your Milestones In Primavera P6 || Easy To Focus Milestones In Schedule



In this tutorial, let us learn about the Best way to show all your milestones in Primavera P6.

 A Smart layout is the one which shows all of your project milestones together in a single WBS element right at the top of the project.

This will enable your top management to view the main part of your schedule clearly.

So, you should add a WBS element called "Milestones" at the top of the project.

Either cut and paste or move all your project milestones into the WBS element.

If your schedule is of bigger size, it would be a tedious job to move all your milestones.

So, now let us do this in a simple way by using Global Logic.

1. Let us open the fresh schedule, before doing anything make a copy of this project.

2. Go to Menu bar, Go to tools, select Global Logic.

3. Click on the New button, to create a new Global Change and name it as Move Milestones.

4. In the IF box, select Any of the following. Under parameter, select Activity Type and under value, select Start milestone. Click on Add button and select Activity Type and under value put Finish milestone.

5. In the Then box, Click on Add button, under parameter select WBS and under value select the WBS element Milestones.

6. Click on Change button and in the preview window click on Commit Changes.

Now, you can see all of your milestones moved under the WBS element milestones.

So, in this way you can move all your milestones as this is the best way to show all your milestones in Primavera P6.

For Personalized detail learning, write to dptutorials15@gmail.com If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***************************************************************
Read my full article on this: http://ift.tt/2kB14dh
***************************************************************
Subscribe for more Awesome Tutorials: goo.gl/4T8ePc
***************************************************************
Support The Channel via shopping: http://ift.tt/2jH38PR
**************************************************************

You Can Connect With Me at
G+ : http://ift.tt/2kAOpa6
Twitter : https://twitter.com/dptutorials15
Facebook : http://ift.tt/2kfRnDi
Blogspot : http://ift.tt/2kB14dh

Comments

  1. Best Casino in South Africa - JCM Hub
    The South African gambling 파주 출장샵 and entertainment capital of South Africa 오산 출장샵 has just celebrated the With the South African casino 세종특별자치 출장샵 at an easy glance 과천 출장샵 and a smile, 안성 출장샵

    ReplyDelete

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad...