Primavera P6 Tutorial : Chapter 2.3 : Resources, Codes and Roles

In this Chapter, let us understand about Resources, Codes and Roles.
Resources include manpower, material and non-material that perform tasks to complete any project. These Resources can be further assigned to different levels of activities in projects.
You can create a Resource database in a hierarchy to reflect particular organization’s resources. To these resources, codes can be established which will help you in grouping, filtering and sorting.
Most importantly, you can setup roles with specific skill sets, which can be used as resource assignments. You can assign prices for all these resources per unit, which will help you in planning costs by resource and roles.
Overview:
Resources:
Start Adding Resources to your database which are required to complete your projects including their limits, unit prices, calendars to define its work hours, shifts. Define the categories of the resources, which will help you at later stage to easily find the related resource from the database.
Roles:
Roles are nothing but your Project personnel like job titles. These can be broadly classified as discipline wise with a hierarchy. These Roles can be assigned with certain resources.
View and Add Resources:
Go to Resource window to view and add resources which are necessary to complete your project. You can add and structure the resources in a hierarchy model to easily classify based on disciplines/ work that perform.
You can set up multiple levels of breakdown structure similar to that of EPS. Include Project managers, Team leaders and other managers in the Resources who fall under non-material category.
To View Resources: Go to Menu Bar, Choose Enterprise, Click Resources tab. Click the display options bar and filter “All Resources” to display to view all the resources available.You can view the complete information of the resource in the description table at the bottom.

To select the resources to display: Click on Display options bar, choose Filter by, choose all Active Resources, All Resources, or current Project’s resources.

To change the view of Resources: Right click on mouse and select the “Chart View” and to customize the details that are being displayed in the chart by right clicking mouse, choose columns and click on customize.

To add Columns to display in the Window: Right Click on Mouse and select columns and add preferred columns.

To Group and Sort: Right click and choose Group and Sort By and choose the predefined or customize base on your preferences.

To Add Resources: Go to Enterprise in the Menu Bar, choose Resources and then click on the add button on the right side of the window “Command Directory” or select any resource available and click insert key on your key board and you will observe that the resource has been added to the next level of the selected resource.

General Information of Resource:
Use the table at the bottom in the resources window to enter general information about the selected resource, which includes Resource ID, Name, employee ID, title, Email address, Office Phone and status.

Details Tab:
Use this tab to specify resource’s classification – labor (personnel), nonlabor (Equipment) and material (supplies); select unit of measurement; assign a calendar to the selected resource; specify the selected resource’s default units/time,

Units and Prices:
Use this tab to specify the limits for the resources. This will help you to identify the resources which are overloaded.

Using Limits: Use this tab to set the limits to delay the start of any resource in the project until the resource is made available.
Progress Reporter:
Use this tab to specify the selected resource’s progress reporter and check the user timesheets to record hours for assigned activities. You must first create the users with logins to use this tab.

Resource Shifts:
You can define Shifts for Resources globally by choosing Enterprise, Resource Shifts, click Add and then type the new Shifts name. To edit any existing shift, click modify.

To Assign Shifts: Choose Enterprise, Resources and go to Units & Prices tab and then select the desired Shift for your resource.
Creating and Assign Resource Codes
Resources codes helps you in categorizing the resources. Assigning these codes to your resources will also help in grouping, filtering and sorting.
To set up codes: Choose Enterprise, select Resource codes, Click add to add any resource code with resource name. To create a hierarchy, click the arrows to indent the selected code. Click modify to change the resource code definition.

Assigning: You can assign resource codes to resources using the Codes tab in Resources details or you can do this by adding a column in the resources window and then assigning code in the column.

Group and Sorting using Resource Codes: Use the Resource Usage spreadsheet to use the resource codes for grouping and sorting the resources.
Setting up Roles
Roles are nothing but your Project personnel like job titles. You can create a standard set of roles which you can assign to labor, nonlabor resources and activities in all projects.

To View Roles: Choose Enterprise, Select Roles click on display options and then filter by either “All Roles” , “Current Project’s Roles”

To View Roles for a specific Resource, go to the resources window and click on details of that resource and in details select the Roles tab.
Adding a Role: Choose Enterprise, Select Roles. Select the role immediately above and at the same level as the role you want to add, then click Add button at the command bar. Use the arrows to adjust the indents to level. For the selected role, you can mention the responsibilities in the roles general tab, you can add up to five price per unit rates for each role in the prices tab, Use the Limits tab to specify available quantities (limits) for a role.

Assigning Roles to Resources
You can assign roles to resources in two ways, either from the Resource Details window or from the Roles dialog box.
  1. From Resource details window: Choose Enterprise, Click Resources, select the resource to which you want to assign a role, click the Display Options bar, then choose Details. Click the Roles tab, then click Assign to assign the roles for that selected resource.

  1. From the Roles dialog box: Choose Enterprise, Click Roles. Click the Display Options bar, then choose Roles Details. Select the role you want to assign. Click the Resources tab, then click Assign resources to the selected role.

Resource Curves

Resource distribution curves enable you to specify how you want resource units spread over the duration of an activity. By default Resource units are distributed evenly during an activity unless you specify nonlinear distribution using curves.
To Add a Custom Resource Curve: Choose Enterprise, Click on Resource Curves. Click Add. Select an existing curve to copy the curve value percentages, then click Select. Type a name for the new resource curve.

Click Modify to define the curve’s distribution. Edit the curve value percentages to create a curve that indicates how your units should distribute over time.

Here is the illustrative video tutorial of the same for your better understanding


Comments

Post a Comment

Popular posts from this blog

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...

Primavera P6 Export To Excel And Color WBS Levels Automatically || How To Color WBS Levels

In this tutorial, let us learn how to Color WBS levels after Primavera P6 Export To Excel. After exporting activity table from Primavera P6 to Excel, it’s very hard to tell which activity belong to which WBS. So in this tutorial, let us see how to color WBS levels automatically so we can have a report like in Primavera P6. This is my sample schedule in primavera, 1. I press Ctrl+A to select entire data and copy the data and then go to Excel sheet and paste it. 2. Add a column left to Activity Id i.e column A and name it as WBS level to show the WBS level for each activity. 3. enter the formula in Cell A2 as = =((FIND(TRIM(B2),B2))-1)/2 4. Hit enter and then apply the same formula to all the cells in column A to see WBS level for each activity. 5. See now, you can view the WBS level for each activity this way easily in Excel after exporting the Primavera P6 Schedule. And Now let us color the WBS levels. 1. Select the entire Data range. 2. Go to Conditional F...

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...