Primavera P6 Tutorial : Chapter 3.0 : Creating a New Project

Let us learn how to create a project in this tutorial.
Step 1: Go to the Menu Bar and click New, to add a new project.

Step 2: In the next screen, a dialog box will be displayed where you need to select the EPS by clicking on the browse button.

Step 3: You need to Name your project here.

Step 4: Here, you can mention the Planned Start date for the new project. You can also mention the Must Finish by Date, but which will be treated as a constraint.

Step 5: You can browse and assign the responsible manager from the OBS that you have developed in the Primavera in the earlier tutorial.

Step 6: Assign the rate types for the pricing of all resources that you would like to use for calculations.

Step 7: Now in the architect window, you can create a project plan from one or more methodologies. Through the architect, you can use the pre-defined template

Step 8: Finally in the last screen, you will receive a congratulatory message.

There by, you can see the newly added project visible in the project explorer window. And at the bottom portion of the window, you can see the detail additional information of all the project related tasks.

Here is the detailed video tutorial for your better understanding:
[paypal_donation_button align="center"]

Comments

Popular posts from this blog

Primavera P6 Tutorial : Chapter 2.7 : User Defined Fields

Apart from the in-built fields available in primavera, you can create User-defined fields which enable you to customize fields and values and add them to the project database. For example, you can use them to track additional activity data such as ordered dates, delivery dates, revised budgets, purchase order / work order numbers, vendor names, etc. In this chapter, let us learn how to create User defined fields, how to work with them and how to work with indicators type of User defined fields. How to Create UDFs? For each custom user defined field you create, you can specify any of the following data formats for that field: Text, Start Date, Finish Date, Cost, Integer, Number, Text, and Indicator. To Define: Go to the Menu bar, Choose Enterprise, select  User Defined Fields . Select the subject area to which you want to add a new field, then click  Add . Double-click in the Title column and type a name for the User Defined Field. Double-click in the Da...

Exporting the Primavera data into excel with same color formatting.

In the earlier posts, we have already seen  how to export the primavera schedule into the excel format and then do the  modifications for further usage. Now, let us see how the schedule in excel looks similar to that of the schedule in the primavera. Here are the steps for the same: Step-1: Open the project in the primavera p6. Step-2: Now, the sample schedule in primavera looks like this as shown below Step-3: Now Press Ctrl+A to select all the rows and columns in the primavera schedule  and C opy all the selected data Step-4: Now go to an excel sheet and right click and select "Paste" option to paste the data that has been copied from the primavera screen Step-5: Insert a user defined column "Level" for filtering purpose and apply filters to all the data. and then filter the Column "Activity name" by checking the "Blanks" -This is nothing but we are filtering all the WBS rows and excluding the activities. ...

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl...