Skip to main content

Primavera P6 Tutorial : Chapter 3.3 : Cost Accounts and Expenses

Cost accounts help you to track activity costs, project expenses and earned value throughout the project life cycle. Cost accounts can be established in a hierarchy available to all projects in the enterprise project structure (EPS).

Overview:

You can create cost accounts that can be assigned to activities in any project. Further, you can also add expenses, assign expense categories and all the details relating to the expenses.
Firstly, create a cost account hierarchy, Go to Menu bar, choose Enterprise, then cost accounts. Click the Cost Account ID column label to display the cost accounts hierarchy.

Setting up a cost account:

Select the cost account immediately above and at the same level as the cost account you want to add, then click Add. Type the cost account’s ID and name and all other information relating to the cost account.
If in case, you wish to use the existing cost accounts, select the project in the top layout, go to project details in the bottom pane and go to defaults tab and in the cost account section, click the browse button and choose the desired cost account.
You can edit, delete the cost accounts by going to the Enterprise>>cost accounts section. You can as well cut/ copy/ paste cost accounts.


Adding Expenses:

Open the desired project for which you want to add expenses.

And then go to Menu bar, choose Project, Expenses to view the expenses tab.

click Add Select the activity that incurs the expense, then click the Select button

Click the General, Activity, Costs, and Description tabs, and enter the expense’s information

Assign an expense category: This type of categories enable you to classify the type of cost and can be used to group, sort, filter, and report the expense and cost information for your projects. In the General tab, then click the Browse button in the Expense Category field. Select the category you want to assign, then click the Select button.

To automatically calculate an expense’s actual cost based on the activity’s completion percentage, mark the Auto Compute Actuals checkbox. Then the module automatically updates the actual/remaining units when project actuals are applied.

Expense accrual type:
Select the expense whose accrual type you want to enter, then click the Activity tab.
Select one of the following accrual types:
■  Start of Activity, to accrue the entire expense on the date the activity begins
■  End of Activity, to accrue the entire expense on the date the activity ends
■  Uniform Over Activity, to evenly distribute the expense over the course of the activity’s duration

Use the General tab to define general information for the selected expense item, such as the item name and category.
Use the Costs tab to specify cost amounts for the selected expense item, including price/unit, budgeted or planned cost, actual cost, and remaining cost
Use the Description tab to enter a description of the selected expense item. You can type a new description. You can use HTML editing features like formatting text, inserting pictures, adding hyperlinks etc.

Analysis:

Comparing actual costs to budgeted values is the simple way to analyse your project status report. Measuring earned value involves three key indicators: planned value, earned value, and actual cost, which is the best way to measure the progress more accurately.
To Run the report wizard, go to menu bar, choose Tools>>Reports>> Reports

And then select a suitable report and then click on “Run Report

The following is the sample report that has been produced using a sample project listing all the expenses of the project budgeted, actual spent and remaining costs. You can as well prepare many reports as per the requirement of the project.

Here is the detailed video tutorial for your better understanding:
[paypal_donation_button align="center"]

Comments


  1. Tag: PM203A52. Let me share all of you about #5 Tips for Project Management Success,, I hope you enjoy it

    1. Plan your day using time management techniques

    As a project manager, time management skills are essential because you are dealing with a wide range of tasks that demand a quick turnaround time. Planning your day will go a long way in keeping you organized and increasing your productivity. Assist your task planning by using project management software which helps you track the work of you and your team.

    If you are not very tech savvy, a simple to-do list can also be a great organizational tool. Prioritize your most important tasks by putting them at the top of the list and less important ones at the bottom. Having a visual plan of your daily tasks helps to keep you on track and aware of time.

    Related post: Free ebook 104 secrets to become a great project manager

    2. Include stakeholders in important project conversations

    While you will have plenty of responsibilities regarding the project, don’t neglect your clients.

    Good communication is essential is keeping both parties informed of project progression, curtailing scope creep, and apprised of changing requirements. Some clients may have different expectations when it comes to communication, so make sure to establish the frequency and type of communication (like emails, phone calls, and face-to-face conversations) at the beginning of your project.

    Establishing communication expectations early helps alleviate stakeholder uncertainty about communication frequency and delivery.

    3. Regularly communicate with your team

    Daily team communication helps keep misunderstandings and unclear requirements under control. Keeping your team informed in every step of the project is essential to project management success.

    For example, a study published by Procedia Technology found that good communication skills were the cornerstone of project management. The study examined over 300 “construction project managers, architects, construction managers, engineers and quantity surveyors” and their successes and failures on various construction projects.

    4. Anticipate project setbacks

    Even the best-laid plans often go awry.

    Remember that even with a high amount of planning and attention to detail, your project may still encounter some challenges. Pay attention to complaints from stakeholders or colleagues, and other warning signs, like a missed deadline or cost overrun, that there may be a problem.

    Preventing a crisis will keep your project running smoothly, save you a lot of time, and keep you, your team, and your stakeholders confident in progressing with the project.

    Unfortunately not every complication can be avoided. Crisis management skills are essential for dealing with the unexpected. Project managers need to be flexible and pragmatic. Improvise and make sharp decisions when needed.

    Related post: 92 free project management templates

    5. Stay focused on the details

    A common problem project managers encounter is having the project aims not aligned with the organization’s objectives. A great project manager will strategize a plan for the project to lead back to the overall success of the business.

    Know your project’s scope by heart and avoid wandering outside of the project’s requirements. It’s too easy to get lost in minor details and forget what your focus is, so a well-planned project scope is essential for success.

    And final, you should use KPI to measure effectiveness of the project, here are full list: 76 project management KPIs



    ReplyDelete
  2. Thanks for your informative article. Softlogic Helo you to get the EXCEL TRAINING WITH PLACMENT IN CHENNAI. More Details Visit the Link

    ReplyDelete
  3. "I loved the post, keep posting interesting posts. I will be a regular reader...

    hairclinic.pk

    ReplyDelete
  4. "I loved the post, keep posting interesting posts. I will be a regular reader...

    Rent a car from Islamabad to Skardu

    ReplyDelete
  5. "I loved the post, keep posting interesting posts. I will be a regular reader...

    yourcar.pk

    ReplyDelete
  6. Thanks a lot for sharing this amazing knowledge with us. This site is fantastic. I always find great knowledge from it. How to Save a Gif from Twitter on Computer

    ReplyDelete
  7. Project Management System Software is the most impactful ERP Software solution that can streamline multiple management processes at your company. This software has amazing features like Attendance Management, Task Management, Employees' Records Management and many more.

    ReplyDelete
  8. Of course its a challenge now a days to provide the good project management services. Your blog has clear few points about this matter, its very beneficial and also your way of presenting and writing is simple and good. Keep it up.

    ReplyDelete

  9. Rent Car Islamabad offers one of the most professional car rental services throughout Islamabad. Rent a Car in Islamabad

    ReplyDelete

Post a Comment

Popular posts from this blog

Top 4 Useful Features, Tricks You Can Use In Primavera P6 || Special features To Learn In Primavera

1. How to Increase the size of icons in Primavera P6?  If you find that the menu bar and command icons are of less visibility, there is a way to increase the size of icons in Primavera P6. Let us see how to do this in this tutorial now. Go to the menu bar and under the view tab, select Toolbars and click on customize. Now a window gets opened like this, go to options tab and tick the checkbox "Large Icons". Click on the Close button and you can see that all your icons now increased in size. 2. How to Animate your Menu Bars in Primavera P6? You know that we have got the option to animate menu bars in Primavera P6. There are 4 animation options in Primavera P6, These are None  Random  Unfold Slide  Fade  You can try any of these if you want a new feel. Follow this steps to Animate Menu Bars. Click on View, go to toolbars, select Customize. Now a customize window will pop up. Go to the options tab, at Menu Animations: Check on Drop Down Bu

How To Merge Two Separate Schedules Into One Master Schedule In Primavera

In this tutorial, let us learn how to Merge two separate schedules into One Master schedule in Primavera P6. In this example, I am considering two separate projects which are these two, One is master schedule and one is the subproject. First, let us open the subproject and export this schedule as a .XER file onto Desktop. and now let us start the exact process of merging two separate schedules. 1. As a first step, We need to open the project schedule into which we want to insert the other project as a sub-project. So, let us open the Master schedule here. 2. Go to Import, select XER format, Click Next 3. Select Project and click Next 4. Now select the Subproject .xer file from the Desktop and click Next 5. Under Import action, select the option as “Update Existing Project” and under import to section, select the Master schedule which is already open. Click Next and Finally Click on Finish. 6. Please note and make sure that your WBS and activity IDs should not confl

How to adjust the Legend Space in Microsoft Project

In this Tutorial, let us see how to adjust the space occupied by the Legends in Microsoft Project, enabling for a better professional print of the schedule. Step - 1: Open the Microsoft Project schedule and go to File>>Print Preview>> Step - 2: At the bottom of the print preview, you can view the Legend portion. Sometimes the legend space occupies the major portion of the page, making it unprofessional to print the schedule reports. Step - 3: So, in order to adjust this legend space,you need to go back to the schedule's Gantt chart view and place the cursor at the gantt chart and right click to select the Bar styles option. Step - 4: Here, you can view all the Legend Labels. Now start entering the symbol asterisk * at the beginning of all the labels which you intend not to reflect in the print view as shown here Now here is the Schedule layout with minimum & only required legends Step -5: Now, in addition to the ad